Path Collective
Roadmap to hard launch
!At risk0 of 102 issues closed
Soft launch · Sep 1At risk
13 open in wave 0 — gates & decisions · 3 weeks left · needs 4.3/week
Hard launch · Dec 1On track
102 open in all waves · 16 weeks left · needs 6.4/week
Red flags (1)
At riskWave 0 (Gates & decisions) is 17 points behind — 0% done with 17% of its window elapsed. 13 open, 35 days left.
Hard launch
112days · Dec 1, 2026
Commercial switches flip: founding-Pro window opens · freemium restrictions activate · PathCoins redemption goes live
Cohort target
100facilitators onboarded
Expecting ~60% highly active · active = 20+ paid bookings/month avg. Growth: 10 (Sept) → 30 (Oct) → 60+ (Nov).
Pre-soft-launch
P0 punch list · #551
in progress
Soft launch
Sept–Nov · 10 → 100
in 21 days
Go / no-go
Month 1 gate
in 56 days
Hard launch
Dec 1 · commercial switches
in 112 days
Wave progress
Wave bar (fill = % issues closed)
Milestone
Today
Hard launch (Dec 1)
Click a wave for details
Live status from GitHub · 0 issues · refreshed never · stale — last refresh failed (GitHub issues fetch 404: {"message":"Not Found","documentation_url":"https://docs.github.com/rest/issues/issues#list-repository-issues","status":"404"})
Source: ROADMAP.md & PRD (2026-08-03) · Meta-issue #547 is the live checklist · Timeline anchored to hard launch 2026-12-01